Masterplan update
 
Road Works





 








  

Road infrastructure works around the Glasgow Harbour site continue to make good progress and are expected to be completed in February 2008.

To minimise any inconvenience, sections of the road are being re-opened to the public as work is completed.

The next phase of the roadworks will finish this month, when the newly re-graded expressway is opened to eastbound traffic. 

The recently completed Partick Link Bridge will be opened to eastbound traffic shortly afterwords.  Westbound traffic will continue to be affected until the final phase.

Hayburn Street improvement works have also started and should be completed by the end of November 2007.

The diversions in place for the Clyde and Loch Lomond Cycleway will continue until the old route is upgraded during January and February 2008.

Roadworks Update - November 2007

Cyclepath/Footpath - November 2007